Westinghouse Road / CR 111 / CR 105 (FM 1460 to SH 130)
|
Description
|
The project will upgrade the existing roadway to a two-lane roadway with shoulders, and provide preliminary planning for an ultimate six-lane divided urban roadway, for the east-west transportation corridor of Westinghouse Road/CR 111, CR 110, and CR 105 (collectively referred to as CR 111).
|
Status
|
Design has been completed by Steger Bizzell. ROW acquisition is complete, and utility coordination is underway. The contractor is Capital Excavation. Construction began in early 2022 and is anticipated to be completed late 2023.
|