Location
|
CR 366
(Chandler Road to Carlos G. Parker Boulevard Northwest)
|
Description
|
This project was requested by the City of Taylor. The project will upgrade the existing two-lane roadway to a three-lane roadway with a continuous center turn lane and shoulders from Chandler Rd to just north of Carlos G. Parker Blvd NW. The intersection with Carlos G. Parker Blvd NW will be realigned to eliminate the existing curve and upgraded to five lanes including turn lanes and shoulders.
The project received construction funding through the voter-approved 2019 Road Bond.
|
Status
|
Detailed
design is being finalized by Garver and is expected to be complete in spring
2022, along with right-of-way acquisition and utility relocation. Construction
is expected to begin in spring 2022 with completion anticipated in spring 2023. For a project fact sheet, click
here.
|
Contact
|
E-mail [email protected] or phone 512-943-1195.
|